April 2023 Project Photos Dewatering tanks. Flatiron Constructors placing concrete for drilled shafts at Abutment 2. A laser level was used during concrete placement to determine top-of-shaft elevation. Vivid Engineering performing quality control testing on the drilled shaft structural concrete. Air content, slump, temperature, and unit weight testing was performed on each truckload of concrete, as required. Flatiron Constructors placing concrete for drilled shafts at Abutment 2. A concrete pump was used to place concrete in the bottom of each shaft. Snow’s Specialty Drilling performing drilling of 24-inch diameter shafts at Abutment 1. Flatiron Constructors installing an elliptical reinforced concrete pipe (RCP). This culvert will gather runoff generated along Moraine Ave, the new roundabout, and portions of Riverside Dr. Flatiron Constructors placing concrete for drilled shafts at Abutment 1. A laser level was used during concrete placement to determine top-of-shaft elevation. GRL Engineers performing integrity testing on the Pier 1 drilled shafts. Flatiron Constructors tying transverse reinforcing steel on the Pier 1 columns. The columns are a continuation of the drilled shaft foundation. Vivid Engineering performing in-place density testing on culvert backfill for a bypass culvert. Encon Colorado placing concrete for prestressed concrete slab girders. Five girders were cast at a time in a single, 275’-long casting bed. Encon Colorado performing tensioning of stressing strands for prestressed concrete slab girders.